Project Synopsis Liquefied natural gas (LNG) Combined Cycle Power Generation
  Main Equipment :
Power Block

Phase-1, Block-1
2 GT 9341 FA+ 2 HRSG + 1 ST
Multi Shaft Combined Cycle module

1940 MW

640 MW



Phase-II. Block-2
2 GT9351FA+ + 2 HRSG + 1 ST
Multi Shaft Combined Cycle module

650 MW
Phase-II. Block-3
2 GT9351FA+ + 2 HRSG + 1 ST
Multi Shaft Combined Cycle module
650 MW



LNG Block 5MMTPA
Regasification Plant

3 Cryogenic storage tanks of 1,60,000 CUM each 2 parallel trains (HP & LP)

Fuel Jetty Suitable for carrier of capacity 80000- 140000 CUM
Breakwater 2.3 Km long rubble mound to control the wave condition
  Other Details :


 Environment Policy
 